3 Answers
You need 1.5 cu. yds. of concrete. To compute that: 120 cu. ft. divided by 1/3 ft.(4 in.=1/3 ft.)=40 cu.ft
and in 1 cu. ft. there are 27 cu. ft. so, 40 divided by 27 is 1.49 cu.yd. (so order 1.5 cu. yd.)
Do not be surprised if you cannot order less than a minimum order of perhaps 2 or 3 cu. yds. to get delivery. So if that is the case, plan on doing additional projects at the same time, build a sidewalk, etc. Do your homework, and plan accordingly!
| 13 years ago. Rating: 2 | |
Top contributors in Do It Yourself (DIY) category
Unanswered Questions
2b8us
Answers: 0
Views: 3
Rating: 0
M88 - M88 Com - ลิงค์เข้าบ้าน M88 เชื่อถือได้ #1 10/2025
Answers: 0
Views: 4
Rating: 0
12BET
Answers: 0
Views: 11
Rating: 0
Căn hộ Happy One Mori
Answers: 0
Views: 11
Rating: 0
xoso6600today1
Answers: 0
Views: 7
Rating: 0
jiliparkstore
Answers: 0
Views: 7
Rating: 0
Raz TN9000
Answers: 0
Views: 5
Rating: 0
188JILI
> More questions...
Answers: 0
Views: 5
Rating: 0
thunderbucky
bustieone
Rob Green