3 Answers
You need 1.5 cu. yds. of concrete. To compute that: 120 cu. ft. divided by 1/3 ft.(4 in.=1/3 ft.)=40 cu.ft
and in 1 cu. ft. there are 27 cu. ft. so, 40 divided by 27 is 1.49 cu.yd. (so order 1.5 cu. yd.)
Do not be surprised if you cannot order less than a minimum order of perhaps 2 or 3 cu. yds. to get delivery. So if that is the case, plan on doing additional projects at the same time, build a sidewalk, etc. Do your homework, and plan accordingly!
| 13 years ago. Rating: 2 | |
Top contributors in Do It Yourself (DIY) category
Unanswered Questions
The Urwerk Time Hunter X-Ray, A New Take On The EMC
Answers: 0
Views: 4
Rating: 0
Inside The Workshops Of Philippe Dufour, F.P. Journe, And Roger Smith
Answers: 0
Views: 7
Rating: 0
Upptäck Elegansen hos Cartier Santos de Cartier Klocka i Roséguld
Answers: 0
Views: 11
Rating: 0
hitclubgraphics1
Answers: 0
Views: 10
Rating: 0
The Linde Werdelin 3 Timer Rock And The 3 Timer Rock Gold
Answers: 0
Views: 8
Rating: 0
De Tijdloze Schoonheid van de Rolex Oyster Perpetual 31 Tiffany Blue
Answers: 0
Views: 10
Rating: 0
taipan77id
Answers: 0
Views: 10
Rating: 0
Lart de la fabrication des roulements en pierres précieuses à Microlap et la montre Breitling Navitimer
> More questions...
Answers: 0
Views: 10
Rating: 0
thunderbucky
bustieone
Rob Green