3 Answers
HI THE CIRCUMFERANCE OF A CIRCLE IS Pi x D = 22/7 X 4 KEEP YOUR DIMENSIONS TO FT AS ITS EASIER
THEREFORE THE TOTAL VOLUME OF YOUR PIPE IS 22/7 X 4 X 1/3 X 20 = 84 cu ft approx
DEPENDING ON YOUR CONCRETE PIPE MIX SAY 150 lbs per cu ft
THIS GIVES APPROX 12600LBS = APPROX 6 IMP TONS
Concrete, Asphalt 140 pounds/cubic foot
Concrete, Gravel 150 pounds/cubic foot
Concrete, Limestone w/Portland 148 pounds/cubic foot
AS COLLEEN SUGESTS YOU WOULD BE BEST CONTACTING A MANUFACTURER AS THERE ARE VARIOUS TYPES OF PIPE AVAILABLE EG STANDARD, REINFORCED, LIGTWEIGHT ETC
HOPE THIS GIVES YOU SOME IDEA ANYWAY
MONDEOMAN
| 14 years ago. Rating: 1 | |
Top contributors in Education & Reference category
Unanswered Questions
Bd9lat
Answers: 0
Views: 18
Rating: 0
Bd9lat
Answers: 0
Views: 14
Rating: 0
123bwinz com
Answers: 0
Views: 20
Rating: 0
A Practical Guide to Sourcing Quality Power Tools from Overseas Suppliers
Answers: 0
Views: 17
Rating: 0
Is Lobster House slot Pragmatic Play RTP strong in Ipswich?
Answers: 0
Views: 19
Rating: 0
68WIN ca cuoc bac nhat tai nuoc ta va khu vuc Chau A
Answers: 0
Views: 19
Rating: 0
68WIN ca cuoc bac nhat tai nuoc ta va khu vuc Chau A
Answers: 0
Views: 17
Rating: 0
68WIN noi bat nhu mot diem den quen thuoc
> More questions...
Answers: 0
Views: 22
Rating: 0
grandpacrabby
MONDEOMAN
Colleen
caddam