Production estimates for July are as follows.
Estimated inventory (units), July 1 8,500
Desired inventory (units), July 31 10,500
Expected sales volume (units), July 76,000
For each unit produced, the direct materials requirements are as follows:
Direct material A ($5 per pound) 3 pounds
Direct material B ($18 per pound) 1/2 pound
The total direct materials purchases of material A and B (assuming no begining or ending inventory) required for July production is:
A: $1,080,000 for A; $648,000 for B
B. $1,080,000 for A; $1,296,000 for B
C. $1,170,000 for A; $702,000 for B
D. $1,125,000 for A; $675,000 for B
2 Answers
Top contributors in Uncategorized category
Unanswered Questions
스포츠 토토사이트 순위 및 추천 사이트, 먹튀 검증 Top15
Answers: 0
Views: 5
Rating: 0
lc88commx
Answers: 0
Views: 3
Rating: 0
36GG
Answers: 0
Views: 4
Rating: 0
88xxbest
Answers: 0
Views: 11
Rating: 0
CCNA Classes in Pune with Live Labs and Expert Trainers
Answers: 0
Views: 8
Rating: 0
ckwin
Answers: 0
Views: 9
Rating: 0
Sunwin - sảnh cá cược thể thao & casino hấp dẫn nhất
Answers: 0
Views: 6
Rating: 0
CCNA Course in Pune Designed for Real-World Network Challenges
> More questions...
Answers: 0
Views: 9
Rating: 0
Linnie4352
country bumpkin